Launching of steel girder for construction of Jetalpur ROB Nr. Vadodara Railway Station on 6 Electrical Railway Track. Launching work completed in half the time then allotted by Railway silent features of road over bridge. |
(1) Launching of steel girder were done with the help of two cranes of 200 MT. & 180 MT. capacity. |
(2) Total 5 girders each having 32 Mtr. Length and 22.5 Mtr. Weight. |
(3) Height of erection 14.9 Mtr From G.L. and girder height 2.2 Mtr. |
(4) Time required to complete the bridge 14 months. |
(5) Total cost of project Rs. 3.10 crore without the cost of girders. |
(6) The girder are supply by Railway in three parts of 10.66 Mtr. and assembled & riveted at site. |
|
 |
|
 |